Volunteers kept Rec Plex on budget and on schedule in 1991

By Joan Janzen

Thirty-five years ago, construction of the Kindersley Rec Plex was underway in November 1991. Figures showed that over a five-week period, services in kind totalled $73,927.75. Donations of material totalled $19,079. Free labour amounted to $10,751.25. Donated use of equipment was valued at $44,097.50.

Volunteers were booked two weeks in advance through a book at the site office, which listed the workers and their areas of expertise. The services in kind took some of the weight off the finance committee, since donations had not yet started pouring in.

Many hands, heavy iron. The Kindersley Rec Plex was on budget and on schedule in November 1991, thanks to countless volunteers and donated use of equipment. Piles were being installed to get the building off the ground by the end of the month. As many tenders as possible were awarded to local contractors. PHOTO COURTESY KINDERSLEY CLARION, NOVEMBER 13, 1991

Previous
Previous

Women in business share advice at Kindersley panel

Next
Next

Honkings from the Wild Goose: Red Wings goaltender covers the puck